CSI Division 31 · Civil & Sitework
Sitework Estimating
Everything outside the building line the architectural set stops short of showing — curbs, walks, pads, fencing, erosion control and final restoration.
- LF
- curb, fence, edging
- SF
- walks, pads, hardscape
- AC
- restoration and seeding
- EA
- signs, bollards, site furnishings
Scope
What we measure.
Measured from
Site plans, civil details and the landscape and hardscape plans
- 01Curb & Gutter
- 02Sidewalk · 4" Concrete
- 03Fencing
- 04Pavement Marking & Signs
- 05Site Restoration
Where bids go wrong
What other sitework estimates miss.
- 01
Everything outside the building line that the architectural set stops short of showing.
- 02
Site concrete formwork, jointing and finishing, priced separately from the flatwork area.
- 03
Traffic control, phasing and access maintenance on an occupied site.
- 04
Final restoration, seeding and the punch-list return visit after the building trades leave.
Sample takeoff
How sitework line items come back.
Every quantity is traceable to the sheet it came from, in the units the trade buys in.
- Quantities traced to the sheet they came from
- Waste and productivity carried as visible lines
- Formulas intact — edit any rate
=ROUND(C4*D4*(1+$E$2),2)| CSI | Line item | Quantity | |
|---|---|---|---|
| 2 | 32 16 13 | Curb & gutter | 1,240 LF |
| 3 | 32 16 23 | Sidewalk — 4" conc. | 3,180 SF |
| 4 | 32 31 13 | Fencing | 860 LF |
| 5 | 32 17 23 | Pavement marking & signs | 1 LS |
| 6 | 32 90 00 | Site restoration | 1.8 AC |
FAQ
Sitework Estimating, answered.
Talk to an estimator
Not a salesperson. Same-day answers on working days.
+1 518 974 7222[email protected]What does sitework include?
Site demolition, clearing, erosion control, site concrete, fencing and site furnishings, each measured as its own scope.
Do you include erosion control?
Yes. Silt fence, inlet protection and construction entrances are measured from the erosion control plan.
Can you use our cost book and labor rates?
Yes, and we prefer it. Your historical costs reflect your crews and your suppliers better than any published average. Send the template and we work inside it.
How does pricing work?
Pricing is per project and quoted before any work starts — no retainer, no minimum volume and no subscription.
Do you sign NDAs?
Yes. Drawings, specifications and pricing are treated as confidential by default, and we sign your NDA on request before any documents change hands.
Same division
More in Civil & Sitework.
- CSI 31Earthwork EstimatingCut, fill and export by state, with shrink and swell treated as three different numbers, and…View
- CSI 33Utilities EstimatingPipe by size, material and depth, with structures, valves and hydrants — the same pipe at…View
- CSI 32Paving EstimatingAsphalt by tonnage from area, thickness and mix density, with base, subgrade preparation, joints and the…View
- CSI 32Landscaping EstimatingPlants by size and count with beds, sod and irrigation, plus the soil preparation beneath every…View
Start a quote
Need sitework numbers for your next bid?