What Is a Quantity Takeoff?
A quantity takeoff is the measured list of materials a construction project needs, taken from its drawings. It counts items, measures lengths, calculates areas and volumes, and groups the results by trade so they can be priced. The takeoff is the foundation of every estimate, because pricing can only be as accurate as the quantities behind it.
Last updated
What does a quantity takeoff measure?
A takeoff measures four kinds of quantity: counts, lengths, areas and volumes. Doors, fixtures and devices are counted. Pipe, conduit, curbs and trim are measured by length. Drywall, roofing and flooring are measured by area. Concrete and earthwork are measured by volume.
Which units do different trades use?
Measuring in the unit a trade buys and installs in avoids conversion errors later.
| Trade | Typical units |
|---|---|
| Concrete | Cubic yards (CY) |
| Rebar and structural steel | Tons or pounds |
| Drywall, roofing, flooring | Square feet (SF), squares for roofing |
| Electrical and plumbing | Each (EA) for devices, linear feet (LF) for pipe and conduit |
| Ductwork | Pounds by gauge |
| Earthwork | Cubic yards of cut and fill |
How is a takeoff done?
Most takeoffs today are done on screen with software such as Bluebeam Revu or PlanSwift. The estimator traces areas and runs on the PDF drawings, and each measurement is colored and labeled so it can be checked.
Good practice is to measure sheet by sheet and trade by trade, keep waste separate from net quantities, and reference every quantity to the sheet it came from.
What are common takeoff mistakes?
- Measuring from a superseded drawing revision
- Missing items shown only in details or schedules
- Double counting where plans and sections overlap
- Applying one waste factor to every material
- Forgetting openings, deductions or height changes
Bid due this week?
Send the plans and bid date today. You get a fixed fee and delivery time before any work starts.
Frequently asked questions
A takeoff measures quantities. An estimate prices them.
Yes. Almost all takeoffs are now done from PDFs with on-screen software.
It depends on the size of the set and the number of trades. Nova delivers most takeoffs in 24 to 48 hours.
Show it separately from net quantities, so it can be adjusted by material and by contractor.
Quantities by item and unit, with the drawing references they came from.
No. A takeoff lists quantities, while an estimate adds prices, labor and markups.
Which estimating service helps with this?
-
Construction Estimating
Priced estimates across every CSI division
-
Quantity Takeoff
Measured quantities with color-coded markups
-
Pre-Construction
Budgets before there is a full drawing set
-
Bid & Procurement
Bid packages, scope sheets and bid leveling
-
Construction Cost Consulting
Independent cost reviews and change order pricing
-
Dedicated Estimating
A named estimator working only your bids
-
Specialized Services
BIM, scheduling and insurance repair estimating
Ready to price your next bid?
Tell us what you are bidding in three short steps. We reply with a fixed fee and a delivery date before any work starts.